RENCANA ANGGARAN BIAYA ( RAB )
PEKERJAAN : REHABILITASI ATAP KANOPI RADIOLOGI DAN SALURAN AIR RUMAH SAKIT UMUM DAERAH "dr.REHATTA"
LOKASI : KABUPATEN JEPARA
TAHUN ANGGARAN : 2024
VOLUME :
NO URAIAN PEKERJAAN VOLUME ANALISA "HARGA SATUAN
Rp." "JUMLAH HARGA
Rp." (PPN) 11% "JUMLAH HARGA KENA PAJAK
Rp."
I PEKERJAAN ATAP
1 Pemasangan atap galvalum 65.63 m2 dihit 75,000.00 4,922,250.00 541,447.50 5,463,697.50
2 Pemasangan 1 m2 rangka besi hollow 34x34 65.63 m2 dihit 179,454.00 11,776,668.75 1,295,433.56 13,072,102.31
3 Pemasangan 1m' Pipa Galvanis Ø 3" 11.20 A.5.1.1.23 455,427.50 5,100,788.00 561,086.68 5,661,874.68
4 Pemasangan 1m' Pipa PVC Ø 6" 33.08 m2 dihit 75,000.00 2,481,000.00 272,910.00 2,753,910.00
5 Pemasangan 1m' Pipa PVC Ø 3" 5.88 m2 dihit 65,000.00 382,200.00 42,042.00 424,242.00
6 Pemasangan overloop dan elbow 2.00 m2 dihit 64,000.00 128,000.00 14,080.00 142,080.00
SUB TOTAL 27,517,906.49
II PEKERJAAN TANAH
1 "Galian tanah
" 9.10 m3 A.1.5.1.1 81,950.00 745,745.00 82,031.95 827,776.95
2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP Muntilan 9.10 m3 A.4.4.1.11.2 142,895.50 1,300,349.05 143,038.40 1,443,387.45
3 Pemasangan 1m2 Plesteran 1 Pc : 3 Pp muntilan Tebal 15 mm 7.56 m3 A.4.4.2.3 80,287.90 606,976.52 66,767.42 673,743.94
4 Pemasangan 1m2 Acian 7.56 m3 A.4.4.2.27 42,322.50 319,958.10 35,195.39 355,153.49
SUB TOTAL 3,300,061.83
TOTAL 30,817,968.32
DIBULATKAN 30,817,000.00